When to order your team kits (count backwards from kickoff)
Allow 25–30 days from confirmed order to delivery — more than 95% of MOMUTO orders arrive inside that window. But teams spend 2–3 weeks deciding before they order, so start 7–9 weeks before kickoff and confirm the order 4–5 weeks out. In a hurry, a fast lane (+€59) saves roughly 7 days.
The backwards count
Your team doesn’t have a kit deadline. It has a kickoff date, and an arithmetic problem nobody has done yet. Here it is, done:
| Step | Time to reserve |
|---|---|
| First fixture | — |
| Shipping | 10–15 days |
| Production | 7–12 days (fast lane: −7) |
| Planning: design vote, sponsor approval, payments | 2–3 weeks |
| Start the process | 7–9 weeks before kickoff |
| Confirm the order | 4–5 weeks before kickoff |
The fixed half: 25–30 days, and it holds
Once an order is confirmed, the clock is predictable: production takes 7–12 days (printing, cutting, sewing, quality control) and shipping 10–15 days, door to door, worldwide. More than 95% of our orders arrive within the 25–30-day window; the exceptions have clustered around global logistics shocks and peak-season capacity, not ordinary orders. If the calendar is against you, the fast lane (+€59) skips the production queue and adds shipping priority — it saves roughly 7 days.
The half nobody budgets for
What our orders actually show: the average team spends 2–3 weeks between “this is our design” and a confirmed order — longer than the production run itself. Four things have to finish first, and only one of them is fast:
1. The design vote. Several options, everyone has taste, a loop is natural. Enjoy it — but give it a deadline.
2. The sponsor. The single biggest source of delay we see. Sponsors want to see the mockup and often ask for changes to their logo’s size or position. Send them the mockup early, not last.
3. The money. Someone is always late paying the captain, and the order can’t be confirmed until the pot is full.
4. The sizes — under 24 hours, almost always. The stage everyone fears is the one that flies: by then the squad is excited and answers fast. The size list is not your bottleneck. The sponsor’s logo is.
“Production is the part people worry about, and the part that never surprises us. The weeks before the order are where the time goes: the vote among teammates, the sponsor who wants the logo shown differently, the payments trickling in to the captain. Each one adds a delay nobody planned for.”
— Alberto, founder, MOMUTO
One thing you don’t need to budget for: logo quality. Every crest and sponsor logo — uploaded to the 3D designer or sent in a brief — is cleaned and print-prepared by a designer before production. A screenshot from the club’s old website is our problem, not yours.
Mapped onto the real calendar
England, France, Spain, Italy — seasons kick off in September: start choosing in early July, confirm by the end of July.
Germany — Kreisliga seasons start early-to-mid August: start by early June, confirm by early July.
US fall leagues — first matches late August–September: start by early July.
Winter leagues, tournaments, corporate events — same count: first match minus 7–9 weeks.
If you are already late
Late is normal — it is the statistically expected output of how groups decide (we wrote about why). The honest options, fastest first:
1. Ready to Play. The longest stage — the design decision — is already done: every design on the wall is finished by our design studio. Pick one, add your crest and numbers, order. Customize deeply or order it as it stands.
2. The fast lane (+€59) — roughly 7 days back.
3. The 3D designer with a hard internal deadline. Free and live — but give the group a decision date, not an open vote.
4. Bespoke (€15 deposit, credited in full from 5 jerseys) — first mockup in 24–48h, and the files are production-ready the moment the order is confirmed.
Frequently asked questions
How long does a custom football kit take?
Production 7–12 days plus shipping 10–15 — typically 25–30 days door to door, worldwide. More than 95% of MOMUTO orders arrive within that window.
When should we order jerseys for a September season start?
Confirm the order by the end of July. Start choosing the design in early July — the team's own planning (design vote, sponsor approval, collecting payment) averages 2–3 weeks, longer than production itself.
What takes the longest?
Not production, and not sizes — size lists usually arrive in under 24 hours. The slow parts are the design vote, the sponsor's mockup approval, and collecting everyone's payment. Plan those first.
We need kits in under four weeks — is it possible?
Often, yes: a Ready to Play design (the design decision is already made) plus the fast lane (+€59, saves roughly 7 days). Contact us with your date before ordering.
Do you check the logos we upload?
Yes — every crest and sponsor logo is cleaned and print-prepared by a designer before production, whether it came through the 3D designer or a design brief.
Is there a minimum order?
No. One jersey (€38.90) or a full squad (from €21.90 each at 10+).